Uganda targets 2027 financial close for Malaba-Kampala railway project…reports Africa Daily News Desk
Uganda is targeting financial close for its 272-kilometre Malaba-Kampala Standard Gauge Railway (SGR) project in 2027, with full construction expected to begin after the issuance of a Notice to Proceed. The government says around 60 per cent of the land required for the railway corridor has been acquired, while preparatory works were completed in October 2026.
Uganda is working towards securing financing and commencing full-scale construction of its long-delayed Malaba-Kampala Standard Gauge Railway (SGR) project, with the government expecting to issue the full Notice to Proceed in early 2027.
The 272-kilometre railway line, which will connect Malaba on the Kenyan border to Kampala, is a key infrastructure priority aimed at linking Uganda to Kenya’s railway network and the port of Mombasa. The project is expected to improve regional transport connectivity and access to international markets.
The update was presented by Minister of Works and Transport Byamukama Fred in a statement to Parliament responding to a question raised by Busuju County MP Lukyamuzi David Kalwanga.
Financing and construction arrangements
The government signed an Engineering, Procurement and Construction (EPC) contract with the Yapi Merkezi-YM Global joint venture on 14 October 2024. The contract is valued at approximately EUR 2.702 billion (UGX 12.31 trillion), with the project’s official launch taking place on 21 November 2024.
The four-year construction period will begin following effective commencement of the main works, subject to the availability of financing.
Uganda plans to source approximately 58 per cent of the project funding through Export Credit Agencies, 25 per cent from development finance institutions and the remaining 17 per cent through government contributions.
The Islamic Development Bank approved EUR 650.75 million (approximately UGX 2.96 trillion) for the project on 16 June 2026, while the OPEC Fund for International Development has completed its appraisal process. Negotiations with Export Credit Agencies are ongoing, alongside efforts by the government to mobilise its contribution through a Sukuk arrangement.
The government is also addressing environmental and social issues raised by financiers and completing the remaining lender assessments and approvals. The statement identifies March 2027 as the targeted date for financial close in its financing section, while a later section refers to January 2027.

Preparatory works and land acquisition
To maintain progress while financing arrangements are being finalised, the government issued a Limited Notice to Proceed (LNTP) to Yapi Merkezi.
The preparatory contract, valued at EUR 75 million (approximately UGX 341.63 billion), commenced on 14 May 2025 and was completed in October 2026.
The work covered surveys, geotechnical investigations, preliminary and selected detailed designs, utility identification and coordination, and the establishment of construction facilities at Iganga. These included a camp, batching plant, precast yard, sleeper factory and laboratory, alongside the procurement of essential equipment.
Land acquisition remains another major component of the project. The railway corridor requires approximately 3,536.26 acres and affects around 12,946 people.
According to the statement, compensation has been paid to 7,721 affected persons, covering approximately 2,108.93 acres, or around 60 per cent of the required land. The government has disbursed UGX 373.07 billion against a total assessed compensation requirement of UGX 845.52 billion, leaving approximately UGX 472.45 billion outstanding.
Land acquisition is most advanced along the Malaba-Mayuge section, where approximately 98 per cent of a continuous corridor has been secured. The government said around 130 kilometres of the railway corridor was available for the contractor to begin work.
An allocation of approximately UGX 221 billion has been provided for compensation in the 2026/27 financial year, with the ministry continuing discussions with the Ministry of Finance, Planning and Economic Development over additional funding.
Regional connectivity and next steps
Beyond the eastern route, preparatory studies are progressing for the Northern Route, covering approximately 762 kilometres towards South Sudan and the Democratic Republic of Congo. Studies are also under way for the Western and Southern routes, spanning approximately 663 kilometres towards the Democratic Republic of Congo and Rwanda.
Planned railway and lake-port connections are expected to support links with the Central Corridor and the port of Dar es Salaam.
The Ministry of Works and Transport is also coordinating with the Ministry of Energy and Mineral Development and the Uganda Electricity Transmission Company to arrange the 25 kV electric traction supply, including grid connections, substations and transmission-line extensions.
Other priorities include cross-border interoperability, staffing, maintenance, safety, asset management and operational arrangements, with engagement continuing with affected communities and local authorities.
The government’s immediate priorities include completing outstanding financing assessments and environmental clearances, compensating affected landowners, securing construction-ready sections of the railway corridor and finalising utility and operational arrangements.
The government maintains that it remains committed to delivering the Malaba-Kampala railway and developing its regional connections, with the full construction programme expected to run for four years after effective commencement.